Urban Redevelopment Project "Residential x Commercial x Plaza" in front of JR Joban Line Kitakogane Station: Announcement of New Construction Start for Kitakogane Station South Exit East District Type 1 Urban Redevelopment Project

The Kitakogane Station South Exit East District Urban Redevelopment Association, with participation from Nomura Real Estate Development Co., Ltd. and Haseko Corporation, announced the start of construction on April 1, 2026, for the "Kitakogane Station South Exit East District Type 1 Urban Redevelopment Project" in Matsudo City, Chiba Prefecture. This approximately 0.9-hectare project, located at the south exit of JR Joban Line Kitakogane Station, is a mixed-use development including residential, commercial facilities, and a plaza of approximately 1,000 square meters, with completion planned for fiscal year 2028. The project aims to improve disaster prevention, create open spaces, and develop a comfortable living environment, aligning with Matsudo City's compact city development plan.
その他 (都市再開発プロジェクト)NQ 75/100出典:prnews

📋 Article Processing Timeline

  • 📰 Published: April 13, 2026 at 22:00
  • 🔍 Collected: April 13, 2026 at 16:35
  • 🤖 AI Analyzed: April 13, 2026 at 17:39 (1h 4m after Collected)
The Kitakogane Station South Exit East District Urban Redevelopment Association, joined by Nomura Real Estate Development Co., Ltd. and Haseko Corporation, announced the commencement of construction on April 1, 2026, for the "Kitakogane Station South Exit East District Type 1 Urban Redevelopment Project" in Matsudo City, Chiba Prefecture.
The project area spans approximately 0.9 hectares, situated in the south exit area of JR Joban Line "Kitakogane Station" in Matsudo City, Chiba Prefecture. Historically, this area flourished as "Kogane-juku," a post town on the Mito Kaido during the Edo period, and is rich in cultural and historical resources such as Tozenji Temple and Honmyoji Temple. In recent years, the "Kitakogane Station South Exit Type 1 Urban Redevelopment Project," completed in March 1994, transformed it into a vibrant gathering place.
However, the current district faces challenges including narrow roads, aging buildings, underutilized land (such as parking lots), and a lack of parks or plazas for public relaxation, leading to concerns regarding disaster prevention, safety, and comfort. This project aims to resolve these issues by enhancing disaster prevention capabilities, creating open spaces, and developing a comfortable living environment through infrastructure improvements, thereby contributing to the promotion of attractive urban development.
Key features of the project include:
(1) Regional revitalization and compact city development based on the "Matsudo City Location Optimization Plan ~Matsudo's Future Full of Charm~."
(2) It is the first cooperative-led urban redevelopment project in Matsudo City.
(3) The development ensures continuity with the adjacent "Kitakogane Station South Exit District Type 1 Urban Redevelopment Project (completed)."
(4) A plaza of approximately 1,000 square meters will be developed as a community gathering place, creating open space.
Project timeline:
July 2020: "Kitakogane Station South Exit East District Urban Redevelopment Preparatory Association" established.
September 2022: City planning decision.
September 2023: "Kitakogane Station South Exit East District Urban Redevelopment Association" established.
February 2025: Rights conversion plan approved.
July 2025: Demolition work commenced.
April 2026: Main construction work commenced.
Fiscal Year 2028: Completion (planned).
Fiscal Year 2029: Association dissolution (planned).