Taipei MRT East Circular Line Section 4 Breaks Ground; Chiang Wan-an: Committed to Solving Neihu Traffic
Following the groundbreaking of the CF710 section in February, the CF720 section of the Taipei MRT East Circular Line broke ground on April 17, becoming the fourth construction package to commence. Taipei Mayor Chiang Wan-an emphasized his determination to resolve Neihu's traffic issues. This section includes two underground stations, Y33 and Y34, and two shield tunnels, spanning approximately 1.8 kilometers. Upon completion, travel from Neihu Science Park to Shilin Station will take 11 minutes, and to Xiangshan Station, 14 minutes.
📋 Article Processing Timeline
- 📰 Published: April 17, 2026 at 12:28
- 🔍 Collected: April 17, 2026 at 13:01 (33 min after Published)
- 🤖 AI Analyzed: April 17, 2026 at 17:22 (4h 21m after Collected)
Central News Agency
(Central News Agency reporter Chen Yu-ting, Taipei, 17th) Following the groundbreaking of the CF710 section in February, the CF720 section of the Taipei MRT East Circular Line broke ground today, becoming the fourth construction package to commence for the East Circular Line. Taipei Mayor Chiang Wan-an stated that this represents his determination and commitment to solving Neihu's traffic problems.
The Taipei Department of Rapid Transit Systems held the groundbreaking ceremony for the CF720 section of the Circular Line East Section today. Cheng Dao-hsin, director of the Department's First District Project Office, explained that this project section connects to the CF710 section, with a total length of approximately 1.8 kilometers, including two underground stations, Y33 and Y34, and two shield tunnels.
He said that currently, a total of 18 stations on the South and North Circular Lines are under full construction, with actual progress reaching about one-third by the end of March. The East Circular Line, which is divided into 6 sections and a total of 10 stations, still has 2 sections, 3 stations, and 1 depot actively being tendered. Although completion will not increase salaries or reduce work, it will make commuting easier, allowing more time for family and oneself with less travel.
Chiang Wan-an stated in his speech that the CF710 section of the East Circular Line broke ground in February, and the CF720 section followed today, with two projects successfully launched within just two months. This demonstrates his continuous efforts to expand the MRT network and his determination and commitment to solving Neihu's traffic problems, and it is a concrete manifestation of the Taipei team's execution ability.
Chiang Wan-an introduced that the future Y33 station, located in Ruiguang Park, will be built as a landscape architecture, serving as a commuting hub while also providing recreational space for citizens. The Y34 station will also retain the plaza above, allowing citizens to easily walk to Neihu Sports Park and Riverside Park.
He stated that after the completion of the East Circular Line, it will only take 11 minutes to travel from Neihu Science Park to MRT Shilin Station and 14 minutes to Xiangshan Station. This will not only drive local development and significantly shorten commuting times but also represents a crucial step for Taipei to become a top international city. He thanked all sectors for their support in piecing together the Circular Line.
Chiang Wan-an emphasized that construction will inevitably bring traffic impacts, but in addition to formulating detailed traffic maintenance plans, the principle of maintaining existing lane numbers will be adhered to to minimize the impact. Communication with local communities will also be maintained to strive for the project's on-schedule and high-quality completion. (Editor: Li Hsi-chang) 1150417
Choose to stand with the facts, every sponsorship you make is a force to protect press freedom.
Download the Central News Agency "First-hand News" APP to get the latest news instantly.
The text, images, and videos on this website may not be reproduced, publicly broadcast, or publicly transmitted and used without authorization.
(Central News Agency reporter Chen Yu-ting, Taipei, 17th) Following the groundbreaking of the CF710 section in February, the CF720 section of the Taipei MRT East Circular Line broke ground today, becoming the fourth construction package to commence for the East Circular Line. Taipei Mayor Chiang Wan-an stated that this represents his determination and commitment to solving Neihu's traffic problems.
The Taipei Department of Rapid Transit Systems held the groundbreaking ceremony for the CF720 section of the Circular Line East Section today. Cheng Dao-hsin, director of the Department's First District Project Office, explained that this project section connects to the CF710 section, with a total length of approximately 1.8 kilometers, including two underground stations, Y33 and Y34, and two shield tunnels.
He said that currently, a total of 18 stations on the South and North Circular Lines are under full construction, with actual progress reaching about one-third by the end of March. The East Circular Line, which is divided into 6 sections and a total of 10 stations, still has 2 sections, 3 stations, and 1 depot actively being tendered. Although completion will not increase salaries or reduce work, it will make commuting easier, allowing more time for family and oneself with less travel.
Chiang Wan-an stated in his speech that the CF710 section of the East Circular Line broke ground in February, and the CF720 section followed today, with two projects successfully launched within just two months. This demonstrates his continuous efforts to expand the MRT network and his determination and commitment to solving Neihu's traffic problems, and it is a concrete manifestation of the Taipei team's execution ability.
Chiang Wan-an introduced that the future Y33 station, located in Ruiguang Park, will be built as a landscape architecture, serving as a commuting hub while also providing recreational space for citizens. The Y34 station will also retain the plaza above, allowing citizens to easily walk to Neihu Sports Park and Riverside Park.
He stated that after the completion of the East Circular Line, it will only take 11 minutes to travel from Neihu Science Park to MRT Shilin Station and 14 minutes to Xiangshan Station. This will not only drive local development and significantly shorten commuting times but also represents a crucial step for Taipei to become a top international city. He thanked all sectors for their support in piecing together the Circular Line.
Chiang Wan-an emphasized that construction will inevitably bring traffic impacts, but in addition to formulating detailed traffic maintenance plans, the principle of maintaining existing lane numbers will be adhered to to minimize the impact. Communication with local communities will also be maintained to strive for the project's on-schedule and high-quality completion. (Editor: Li Hsi-chang) 1150417
Choose to stand with the facts, every sponsorship you make is a force to protect press freedom.
Download the Central News Agency "First-hand News" APP to get the latest news instantly.
The text, images, and videos on this website may not be reproduced, publicly broadcast, or publicly transmitted and used without authorization.
FAQ
What is the scope of the Taipei MRT East Circular Line CF720 section project?
The CF720 section project continues from the CF710 section, with a total length of approximately 1.8 kilometers. It includes two underground stations, Y33 and Y34, and two shield tunnels.
How will the East Circular Line improve commuting times in the Neihu area upon completion?
Upon completion of the East Circular Line, travel from Neihu Science Park to MRT Shilin Station will take only 11 minutes, and to Xiangshan Station, 14 minutes, significantly shortening commuting times.