[Wistron] Subsidiary Dingchuang Limited Announces Construction of Dormitories and Office Building via Land Lease and Commissioned Building Method
Key facts
- [Wistron] Subsidiary Dingchuang Limited Announces Construction of Dormitories and Office Building via Land Lease and Commissioned Building Method
- Dingchuang Limited, a subsidiary of Wistron, has announced the construction of dormitories and an office building through a land lease and commissioned building arrangement. The project budget has been increased by NT$400 million, bringing the total construction cost to NT$25.37 billion.
- Source: PR Times
- Date: June 26, 2026
Direct answer
Dingchuang Limited, a subsidiary of Wistron, has announced the construction of dormitories and an office building through a land lease and commissioned building arrangement. The project budget has been increased by NT$400 million, bringing the total construction cost to NT$25.37 billion.
- Citation
- [Wistron] Subsidiary Dingchuang Limited Announces Construction of Dormitories and Office Building via Land Lease and Commissioned Building Method (June 26, 2026), PR Times
- Source
- PR Times
- Date
- June 26, 2026
Dingchuang Limited, a subsidiary of Wistron, has announced the construction of dormitories and an office building through a land lease and commissioned building arrangement. The project budget has been increased by NT$400 million, bringing the total construction cost to NT$25.37 billion.
📋 Article Processing Timeline
- 📰 Published: June 26, 2026 at 09:00
- 🔍 Collected: June 27, 2026 at 17:00 (32h 0m after Published)
- 🤖 AI Analyzed: June 27, 2026 at 17:54 (53 min after Collected)
1. Contract Type: Land Lease and Commissioned Construction
2. Event Date: June 26, 2026 ~ June 26, 2026
3. Board Approval Date: June 26, 2026 (Minguo Year 115)
4. Other Approval Dates: Not applicable
5. Contract Counterparty and Relationship with the Company: Not yet determined
6. Main Contract Contents (including total contract amount, expected investment amount, contract start and end dates, restrictive clauses, and other important terms): In response to practical needs for constructing an office building, a budget increase of NT$400 million is proposed, bringing the cumulative construction expenditure to NT$2,537 million.
7. Name of Professional Appraisal Firm or Company and Appraisal Result: Not applicable
8. Name of Real Estate Appraiser: Not applicable
9. License Number of Real Estate Appraiser: Not applicable
10. Specific Purpose of Acquisition: To meet business development and strategic planning needs
11. Dissenting Director Opinions on the Transaction: None
12. Is the Transaction a Related-Party Transaction: No
13. Date of Supervisor Approval or Audit Committee Consent: Not applicable
14. Is the Appraisal Report a Limited Price, Specific Price, or Special Price: No or Not applicable
15. Has an Appraisal Report Not Yet Been Obtained: No or Not applicable
16. Reason for Not Obtaining Appraisal Report: Not applicable
17. Reasons for Significant Differences in Appraisal Results and Auditor's Opinion: Not applicable
18. Name of Accounting Firm: Not applicable
19. Name of Auditor: Not applicable
20. Auditor's License Number: Not applicable
21. Previous Date of Material Information Disclosure on the Same Event: This is an update to the material information originally disclosed on April 20, 2022 (Minguo Year 111), regarding the announcement by subsidiary Dingchuang Limited (abbreviated as Dingchuang) on constructing dormitories and an office building via land lease and commissioned building method.
22. Other Explanatory Matters: The counterparties for civil construction and electrical and mechanical engineering have already been announced in 2022 and 2026.
2. Event Date: June 26, 2026 ~ June 26, 2026
3. Board Approval Date: June 26, 2026 (Minguo Year 115)
4. Other Approval Dates: Not applicable
5. Contract Counterparty and Relationship with the Company: Not yet determined
6. Main Contract Contents (including total contract amount, expected investment amount, contract start and end dates, restrictive clauses, and other important terms): In response to practical needs for constructing an office building, a budget increase of NT$400 million is proposed, bringing the cumulative construction expenditure to NT$2,537 million.
7. Name of Professional Appraisal Firm or Company and Appraisal Result: Not applicable
8. Name of Real Estate Appraiser: Not applicable
9. License Number of Real Estate Appraiser: Not applicable
10. Specific Purpose of Acquisition: To meet business development and strategic planning needs
11. Dissenting Director Opinions on the Transaction: None
12. Is the Transaction a Related-Party Transaction: No
13. Date of Supervisor Approval or Audit Committee Consent: Not applicable
14. Is the Appraisal Report a Limited Price, Specific Price, or Special Price: No or Not applicable
15. Has an Appraisal Report Not Yet Been Obtained: No or Not applicable
16. Reason for Not Obtaining Appraisal Report: Not applicable
17. Reasons for Significant Differences in Appraisal Results and Auditor's Opinion: Not applicable
18. Name of Accounting Firm: Not applicable
19. Name of Auditor: Not applicable
20. Auditor's License Number: Not applicable
21. Previous Date of Material Information Disclosure on the Same Event: This is an update to the material information originally disclosed on April 20, 2022 (Minguo Year 111), regarding the announcement by subsidiary Dingchuang Limited (abbreviated as Dingchuang) on constructing dormitories and an office building via land lease and commissioned building method.
22. Other Explanatory Matters: The counterparties for civil construction and electrical and mechanical engineering have already been announced in 2022 and 2026.
FAQ
What is Dingchuang Limited?
A subsidiary of Wistron Group focused on developing and managing production infrastructure such as factories and dormitories.
What does 'land lease and commissioned building' mean?
A method where land is leased and construction is outsourced, reducing upfront capital burden while securing facilities.
What is the total budget for this construction project?
The cumulative budget is NT$25.37 billion, with an additional NT$400 million recently approved.