CSBC Launches Navy's New Floating Dock, Steadfastly Promoting Indigenous Naval Shipbuilding
Key facts
- CSBC Launches Navy's New Floating Dock, Steadfastly Promoting Indigenous Naval Shipbuilding
- Taiwan International Shipbuilding Corporation (CSBC) announced the launch of a new auxiliary repair dock built for the Navy. The dock, costing approximately NT$860 million, will be used for vessel maintenance and supports the national defense indigenization policy.
- Source: PR Times
- Date: April 10, 2026
Direct answer
Taiwan International Shipbuilding Corporation (CSBC) announced the launch of a new auxiliary repair dock built for the Navy. The dock, costing approximately NT$860 million, will be used for vessel maintenance and supports the national defense indigenization policy.
- Citation
- CSBC Launches Navy's New Floating Dock, Steadfastly Promoting Indigenous Naval Shipbuilding (April 10, 2026), PR Times
- Source
- PR Times
- Date
- April 10, 2026
Taiwan International Shipbuilding Corporation (CSBC) announced the launch of a new auxiliary repair dock built for the Navy. The dock, costing approximately NT$860 million, will be used for vessel maintenance and supports the national defense indigenization policy.
📋 Article Processing Timeline
- 📰 Published: April 10, 2026 at 15:59
- 🔍 Collected: April 10, 2026 at 17:00 (1h 1m after Published)
- 🤖 AI Analyzed: April 20, 2026 at 08:35 (231h 35m after Collected)
CSBC stated that the construction project, signed on August 18, 2023, began construction on May 4, 2024, underwent keel laying on January 9, 2025, and was launched today, meeting the launch condition by February 3, 2026. The total project cost is approximately NT$860 million.
CSBC explained that the Navy's new ARD is a crucial part of the Navy's overall logistics and an important guarantee for subsequent naval vessel maintenance. The dock body is 126 meters long, 36 meters wide, with a maximum draft of 2.5 meters when not submerged and 12 meters when submerged. It can perform repair operations for vessels under 3800 tons without specific limitations.
CSBC noted that the Navy's new ARD features automated buoyancy and submergence functions, a valve control system, and a power management system, providing an integrated monitoring system that allows operators to remotely monitor the status of related equipment, significantly improving operational safety and efficiency. CSBC has fed its practical experience accumulated from recent naval vessel and dock construction, maintenance, and repair projects into this design. Understanding the Navy's logistical needs for floating docks, the company aims not only to 'build' but also to provide 'repair' capabilities, making it more suitable for actual operational requirements.
To effectively execute construction management and warranty responsibilities after delivery, CSBC stated that it has established complete naval vessel design blueprints and introduced a product lifecycle management system, integrating existing management information and building good relationships with equipment manufacturers.
CSBC emphasized that the Navy's new floating dock is an important piece of equipment for subsequent naval vessel preparation and maintenance. To steadfastly promote the national 'Made in Taiwan' shipbuilding policy and defend national sovereignty, CSBC shoulders this responsibility and will uphold its factory-building spirit to be a core driver of the government's localization policy in the shipbuilding industry. (Editor: Lin Shu-yuan) 1150410
FAQ
What are the features of the floating dock that was launched this time?
The floating dock is 126 meters long and 36 meters wide, capable of performing dock repairs for ships up to 3,800 tons, and it has automated and remote monitoring functions.
What is the importance of this floating dock to the Taiwanese Navy?
It is a crucial part of the Navy's overall logistics, effectively ensuring the maintenance and preparation of ships, and supporting the policy of domestically built warships.
What is the total cost and timeline of this project?
The total cost of the project is approximately NT$860 million. The launching ceremony was held today, and it is scheduled to meet the launch conditions by February 3, 2026.