Bielot Group Advances Grid-Scale Battery Storage Projects in Kyoto and Shiga

Key facts

  • Bielot Group Advances Grid-Scale Battery Storage Projects in Kyoto and Shiga
  • Bielot Co., Ltd. announced that its group company, Kumashu Komuten Co., Ltd., has acquired land and grid connection rights for grid-scale battery storage facilities in Kyotango City, Kyoto, and Nagahama City, Shiga. Completion is scheduled for late 2026, with power sales expected to begin in February 2027.
  • Source: PR Times
  • Date: June 11, 2026

Direct answer

Bielot Co., Ltd. announced that its group company, Kumashu Komuten Co., Ltd., has acquired land and grid connection rights for grid-scale battery storage facilities in Kyotango City, Kyoto, and Nagahama City, Shiga. Completion is scheduled for late 2026, with power sales expected to begin in February 2027.

Citation
Bielot Group Advances Grid-Scale Battery Storage Projects in Kyoto and Shiga (June 11, 2026), PR Times
Source
PR Times
Date
June 11, 2026
Bielot Co., Ltd. announced that its group company, Kumashu Komuten Co., Ltd., has acquired land and grid connection rights for grid-scale battery storage facilities in Kyotango City, Kyoto, and Nagahama City, Shiga. Completion is scheduled for late 2026, with power sales expected to begin in February 2027.
その他NQ 80/100出典:PR Times

📋 Article Processing Timeline

  • 📰 Published: June 11, 2026 at 00:36
  • 🔍 Collected: June 10, 2026 at 15:51
  • 🤖 AI Analyzed: June 10, 2026 at 22:38 (6h 47m after Collected)
Bielot Co., Ltd. (Headquarters: Minato-ku, Tokyo; Representative Director: Makoto Miyauchi; TSE Standard: 3452) announced that its group company, Kumashu Komuten Co., Ltd., has acquired land and grid connection rights for grid-scale battery storage facilities.

1. Project Background
Under the long-term vision of its medium-term management plan, the group aims to "contribute to a sustainable society through its business." With the recent expansion of renewable energy, expectations for grid-scale battery storage facilities, which help stabilize power supply and demand, have risen.

In light of this business environment, Kumashu Komuten has acquired land and grid connection rights for projects in Kyotango City, Kyoto Prefecture, and Nagahama City, Shiga Prefecture.

With these projects, the total number of grid-scale battery storage projects being promoted by the group reaches six.

2. Property Overview
Locations:
(1) 1195-2, 4 Noborida, Tomoshige, Kumihama-cho, Kyotango City, Kyoto
(2) 450-1, Morinokuchi, Oji-cho, Nagahama City, Shiga

Maximum Receiving Power:
(1) & (2) 1,979 kW

Connected Utility Company:
(1) & (2) Kansai Transmission and Distribution, Inc.

Site Area:
(1) 971 sqm
(2) 841 sqm

Scheduled Completion:
(1) November 2026
(2) December 2026

Expected Start of Power Sales:
(1) & (2) February 2027

3. Growth of the Grid-Scale Storage Market
According to the "Battery and Power Industry Strategy" released by the Ministry of Economy, Trade and Industry (METI) in June 2026, the stationary battery market is projected to grow at an annual rate of 11.0% through 2035. The government is promoting the adoption of grid-scale energy storage systems through support programs utilizing GX economic transition bonds.

Against the backdrop of this market expansion and policy support, the group is advancing its battery storage business. Through these projects, we aim to achieve both stable business revenue and the realization of a sustainable society, while continuing to create and expand business opportunities in the field of renewable energy.

FAQ

Where are the locations for the new system battery storage project promoted by the Beelot Group?

The locations are 1195-2 and 1195-4, Tomochu, Kumihama-cho, Kyotango City, Kyoto Prefecture, and 450-1-2, Morinokuchi, Oji-cho, Nagahama City, Shiga Prefecture.

When is the planned start date for power sales in this project?

Both projects in Kyoto and Shiga Prefectures are scheduled to start power sales in February 2027.

Which company is the power connection provider for the Kumashu Construction Co., Ltd.?

Kansai Electric Power Transmission and Distribution Co., Ltd.

What is the background for the Beelot Group's promotion of the system battery storage business?

The background includes the expectation of stabilizing power supply and demand with the expansion of renewable energy, and the business opportunity expansion based on market growth forecasts and policy support published by the Ministry of Economy, Trade and Industry.

Including this announcement, how many system battery storage projects is the Beelot Group promoting in total?

Including this project, the total number of system battery storage projects promoted by the Beelot Group is six.