Highwealth Construction (Ai Shan Lin) announced an increase in the contract value for the new construction project at the Jiangcui Section in Banqiao (D2 Project). Due to soaring raw material costs and shortages in labor and materials, the engineering contract with Li Xin Construction will see an addition of NT$370,947,607. Highwealth Construction will cover NT$148,379,043 (40%) of this additional cost. Following the adjustment, the total project cost is estimated at NT$2,837,901,531.