[Century Fengdian] (Supplementary Announcement 115/2/23) Company to Construct Fifth Phase Factory at Taipei Port South Pier via Land Lease and Construction Method
Century Fengdian announced the construction of a new fifth-phase factory at Taipei Port South Pier through a land lease and construction method. The project involves various engineering contracts totaling approximately NT$2.146 billion and is intended for operational use.
📋 Article Processing Timeline
- 📰 Published: April 30, 2026 at 09:00
- 🔍 Collected: May 1, 2026 at 08:00 (23h 0m after Published)
- 🤖 AI Analyzed: May 1, 2026 at 08:24 (24 min after Collected)
1. Contract Type: Land Lease and Construction
2. Date of Occurrence: 115/4/30 ~ 115/4/30
3. Board of Directors Approval Date: December 6, 112 (Republic of China calendar)
4. Other Approval Date: Not applicable
5. Contract Counterparties and Their Relationship with the Company:
Contract Counterparties:
1. Civil Engineering: Xu Yuan Construction Engineering Co., Ltd., etc.
2. Steel Structure Engineering: Century Iron & Steel Structure Co., Ltd., etc.
3. Mechanical and Electrical Engineering: Yong Chen Mechanical & Electrical Engineering Co., Ltd., etc.
4. Color Steel Engineering: Ching Feng Engineering Co., Ltd., etc.
5. Design Fee: Tai A Design Co., Ltd., etc.
6. Foundation Pile Engineering: Xu Yuan Construction Engineering Co., Ltd., etc.
7. Miscellaneous Engineering: Xu Yuan Construction Engineering Co., Ltd., etc.
8. Crane Engineering: Li Chang Enterprise Co., Ltd., etc.
Relationship with the Company: Except for Century Iron & Steel Structure Co., Ltd., which is a related party of the Company, other contractors are non-related parties.
6. Main Contract Contents (including total contract amount, estimated investment amount, and contract start/end dates), restrictive clauses, and other important agreements:
Total Contract Amount:
1. Civil Engineering: NT$224,296,510.
2. Steel Structure Engineering: NT$1,014,018,239.
3. Mechanical and Electrical Engineering: NT$185,000,000.
4. Color Steel Engineering: NT$100,000,000.
5. Design Fee: NT$16,245,000.
6. Foundation Pile Engineering: NT$73,355,950.
7. Miscellaneous Engineering: NT$74,610,606.
8. Crane Engineering: NT$458,512,170.
As of 115/3/31, the cumulative estimated total engineering amount is NT$2,146,038,475.
Contract Start and End Dates: From the date of signing to the date of completion and acceptance.
Restrictive Clauses and Other Important Agreements: None.
7. Professional Appraisal Firm or Company Name and its Appraisal Result:
Not applicable
8. Real Estate Appraiser Name:
Not applicable
9. Real Estate Appraiser Practice Certificate Number:
Not applicable
10. Specific Purpose of Acquisition:
For operational use.
11. Dissenting Board Member Opinions on this Transaction:
Not applicable
12. Is this transaction a related party transaction? No
13. Date of Supervisor's Approval or Audit Committee's Consent:
December 6, 112 (Republic of China calendar)
14. Is the appraisal report a limited price, specific price, or special price? No or not applicable.
15. Have you not yet obtained the appraisal report? No or not applicable.
16. Reason for not obtaining the appraisal report:
Not applicable
17. If there is a significant difference in the appraisal result, the reason for the difference and the accountant's opinion:
Not applicable
18. Accounting Firm Name:
Not applicable
19. Accountant Name:
Not applicable
20. Accountant Practice Certificate Number:
Not applicable
21. Date of previous major announcement regarding the same event:
December 6, 112; March 5, 113; April 17, 114; August 4, 114; November 12, 114;
February 23, 115.
22. Other explanatory matters:
None.
2. Date of Occurrence: 115/4/30 ~ 115/4/30
3. Board of Directors Approval Date: December 6, 112 (Republic of China calendar)
4. Other Approval Date: Not applicable
5. Contract Counterparties and Their Relationship with the Company:
Contract Counterparties:
1. Civil Engineering: Xu Yuan Construction Engineering Co., Ltd., etc.
2. Steel Structure Engineering: Century Iron & Steel Structure Co., Ltd., etc.
3. Mechanical and Electrical Engineering: Yong Chen Mechanical & Electrical Engineering Co., Ltd., etc.
4. Color Steel Engineering: Ching Feng Engineering Co., Ltd., etc.
5. Design Fee: Tai A Design Co., Ltd., etc.
6. Foundation Pile Engineering: Xu Yuan Construction Engineering Co., Ltd., etc.
7. Miscellaneous Engineering: Xu Yuan Construction Engineering Co., Ltd., etc.
8. Crane Engineering: Li Chang Enterprise Co., Ltd., etc.
Relationship with the Company: Except for Century Iron & Steel Structure Co., Ltd., which is a related party of the Company, other contractors are non-related parties.
6. Main Contract Contents (including total contract amount, estimated investment amount, and contract start/end dates), restrictive clauses, and other important agreements:
Total Contract Amount:
1. Civil Engineering: NT$224,296,510.
2. Steel Structure Engineering: NT$1,014,018,239.
3. Mechanical and Electrical Engineering: NT$185,000,000.
4. Color Steel Engineering: NT$100,000,000.
5. Design Fee: NT$16,245,000.
6. Foundation Pile Engineering: NT$73,355,950.
7. Miscellaneous Engineering: NT$74,610,606.
8. Crane Engineering: NT$458,512,170.
As of 115/3/31, the cumulative estimated total engineering amount is NT$2,146,038,475.
Contract Start and End Dates: From the date of signing to the date of completion and acceptance.
Restrictive Clauses and Other Important Agreements: None.
7. Professional Appraisal Firm or Company Name and its Appraisal Result:
Not applicable
8. Real Estate Appraiser Name:
Not applicable
9. Real Estate Appraiser Practice Certificate Number:
Not applicable
10. Specific Purpose of Acquisition:
For operational use.
11. Dissenting Board Member Opinions on this Transaction:
Not applicable
12. Is this transaction a related party transaction? No
13. Date of Supervisor's Approval or Audit Committee's Consent:
December 6, 112 (Republic of China calendar)
14. Is the appraisal report a limited price, specific price, or special price? No or not applicable.
15. Have you not yet obtained the appraisal report? No or not applicable.
16. Reason for not obtaining the appraisal report:
Not applicable
17. If there is a significant difference in the appraisal result, the reason for the difference and the accountant's opinion:
Not applicable
18. Accounting Firm Name:
Not applicable
19. Accountant Name:
Not applicable
20. Accountant Practice Certificate Number:
Not applicable
21. Date of previous major announcement regarding the same event:
December 6, 112; March 5, 113; April 17, 114; August 4, 114; November 12, 114;
February 23, 115.
22. Other explanatory matters:
None.